o. | Projects | Outline | Year |
---|---|---|---|
1 | Survey and Feasibility Study on Vung Ang Steel Plant Project | Transportation system for the plant (Port, Road)
Dredging channel and Turning area Port Facilities |
2005 |
2 | Survey and Feasibility Study on Viet – Italia Steel Plant Project | Port System
Dredging channel and turning area Port Facilities |
2006 |
3 | Survey for post dredging of Viet – Australia Steel Plant | Checking Dredging Depth
Access Road |
2006 |
4 | Survey and Feasibility Study on Thach Khe ore explotion Project | Port for 5,000 – 10,000 DWT vessel
Breakwater Reclaimation |
2006 |
5 | Survey and Feasibility Study and Detailed Design of B12 Oil and Gas Port Project | 3 oil and gas berths
Dredging channel Port Facilities |
2004 |
6 | Construction supervision for Ho Chi Minh City Sanitation Improvement Project | Nhieu Loc – Thi Nghe Basin Channel
Pump station network Embankment Other services |
2004-2007 |
7 | Survey and Feasibility Study on Nha Be PETECHIM port | 2 berths for 25,000 – 45,000 DWT oil vessel
Access Channel Port Facilities |
2005 |
8 | Survey and Feasibility Study on Dinh Vu Oil and Gas Container Terminal | 1 berth for 30,000 DWT oil vessel
Access Channel Port facilities |
2005 |
9 | Survey and Detailed Design and construction supervision of Cua Sot Fishery port Project | 1 fishery port
Access channel Navigation Buoy Aids Port facilities |
2005 |
10 | Survey and Feasibility Study on PTSC Petro container terminal project | 1 berth for 10,000 DWT vessel
Access Channel Port facilities |
2005 |
11 | Survey and master plan for Dac Nong Alumina transportation network | 3 port location
250 km of railway network Other facilities |
2006 |